Question: Using constant low workforce with subcontract, what would be the constant workforce? Production required in periods 1, 2 and 3 respectively are 1,000,1,500 and 1,900

 Using constant low workforce with subcontract, what would be the constant

Using constant low workforce with subcontract, what would be the constant workforce? Production required in periods 1, 2 and 3 respectively are 1,000,1,500 and 1,900 units. One worker during the planning horizon can produce two units in one day, eight-hour workday. Number of workdays are 20, 21, and 23 in periods 1, 2 and 3 respectively. What is the number of workers required during the planning horizon of three periods? O 25 O 40 O 30 50 42