Question: Using cpm method crash the project 4 unit of time (months, weeks, days)Creat yourself all the required data. Activity Predecessor Activity Duration (Weeks) A 3

Using cpm method crash the project 4 unit of time (months, weeks, days)Creat yourself all the required data.
Activity Predecessor Activity Duration (Weeks) A 3 B A 5 A 7 D B 10 E 5 F DE 4Step by Step Solution
There are 3 Steps involved in it