Question: Using data from Questions 1 1 and 1 2 : Add a second shift to the project to reduce the project duration. The 2 nd

Using data from Questions 11 and 12:
Add a second shift to the project to reduce the project duration.
The 2nd shift adds 15% to the cost of labor that works the second shift.
Working the 2nd shift increases the overall productivity of labor on a given calendar day by 87.5%.
What is the optimal combination of lowest possible total cost (in dollars) and minimum total project duration (in days) for this project? Document your crashing strategy, in other words, clearly state which activities should be crashed. Use the following worksheet to document your crashing strategy for each iteration:
Activity
Original duration (d)
Original No. of workers per day
Original total labor per activity (worker-days)
Labor unit cost ($/worker-day)
Original labor cost ($)
Crashed duration (d)
Saved cost by crashing duration ($)
Added cost from 2ndshift (+$)
Net added cost or savings (+/$)
A
5
5
B
9
6
C
7
8
D
3
3
Total

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!