Question: using given informations, Draw ( Sketch) the detailed Work Breakdown Structure WBS. Building Villa Project 1 Level 1 1. Site Work 2 Level 1 2.

using given informations, Draw ( Sketch) the detailed Work Breakdown Structure WBS.

Building Villa Project

1

Level 1

1. Site Work

2

Level 1

2. Sub-Structure

3

Level 1

3. Super-Structure

4

Level 1

4. Finishes

5

Level 1

5. Systems

6

Level 1

6. Handing Over

7

Level 1

1.Site Work

8

Level 2

1.1 Mobilisation of Staff

9

Level 2

1.2 Mobilisation of Machinery

10

Level 2

1.3 Surveying

11

Level 2

1.4 Earth Work Excavation

12

Level 2

1.5 Anti Termite Treatment

13

Level 2

1.6 Filling

14

Level 2

1.7 PCC Below Footings

15

Level 2

1.8 Temporary Fence

16

Level 1

2. Sub-Structure

17

Level 2

2.1 RCC in Sub-Structure

18

Level 3

2.1.1 M-30 in Footings

19

Level 3

2.1.2 M-15 in Plinth Beam

20

Level 3

2.1.3 Footing to Top of Plinth

21

Level 2

2.2 Column Neck

22

Level 2

2.3 Footings

23

Level 3

2.3.1 Shuttering

24

Level 3

2.3.2 Steel Reinforcement

25

Level 3

2.3.3 Concreting

26

Level 3

2.3.4 Curing & Removing

27

Level 2

2.4 Plinth Beam

28

Level 2

2.5 Block Work

29

Level 2

2.6 Water Proofing

30

Level 2

2.7 Back Filling

31

Level 2

2.8 Concreting & Flooring

32

Level 1

3. Super-Structure

33

Level 2

3.1 RCC in Columns

34

Level 3

3.1.1 Column Above Plinth M-15

35

Level 3

3.1.2 Above Plinth M-15

36

Level 2

3.2 RCC M30

37

Level 3

3.2.1 Beams M-30

38

Level 3

3.2.2 Lintels M-30

39

Level 3

3.2.3 Staircase M-30

40

Level 2

3.3 RCC in Slabs

41

Level 3

3.3.1 With M-30 Concrets

42

Level 2

3.4 RCC in Parapet

43

Level 3

3.4.1 M-30 Concrets

44

Level 2

3.6 Masonry Work

45

Level 3

3.6.1 Brickwork

46

Level 1

4. Finishes

47

Level 2

4.1 Plastering

48

Level 3

4.1.1 Ceiling Plaster

49

Level 3

4.1.2 Internal Wall Plaster

50

Level 3

4.1.3 External Wall Plaster

51

Level 3

4.1.4 Water Proofing in Toilets

52

Level 3

4.1.5 Synthetic Plaster

53

Level 3

4.1.6 Brick Bat Coba in Toilets

54

Level 3

4.1.7 Brick Bat Coba over Terrace

55

Level 2

4.2 Flooring

56

Level 3

4.2.1 Kota Flooring

57

Level 3

4.2.2 Marble Flooring

58

Level 3

4.2.3 Kota Treads and Risers

59

Level 3

4.2.4 Marble Treads and Risers

60

Level 2

4.3 Dadoning & Skirting

61

Level 3

4.3.1 Kota Skirting

62

Level 3

4.3.2 Marble Skirting

63

Level 3

4.3.3 Kota Sills

64

Level 3

4.3.4 Grinaite Counter Top

65

Level 3

4.3.5 Doors

66

Level 4

4.3.5.1 Aluminium Panels

67

Level 4

4.3.5.2 Timber Panels

68

Level 4

4.3.5.3 Timber Flush Panels

69

Level 3

4.3.6 Windows

70

Level 4

4.3.6.1 Aluminium Framed Sliding Window with Glass & Fly Screen

71

Level 4

4.3.6.2 Aluminium Framed Fixed Glass Window

72

Level 4

4.3.6.3 Aluminium Framed Louvred window with Fly Screen

73

Level 3

4.3.7 Painting

74

Level 4

4.3.7.1 Texture Paint

75

Level 1

5. Systems & Utilities

76

Level 2

5.1 Water Proof Treatment for RCC Slabs

77

Level 2

5.2 Internal Water Supply

78

Level 2

5.3 Internal Sanitary

79

Level 2

5.4 External Water Supply

80

Level 2

5.5 Rain Water Drainage

81

Level 2

5.6 External Water Drainage

82

Level 2

6.7 Internal Electrification

83

Level 2

6.8 External Electrification

84

Level 1

6. Handing Over

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!