Question: Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8
Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function
Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected:
Month Labor Cost($) Employee Hours
January 9,690 300
February 7,200 350
March 7,731 370
April 8,340 280
May 9,987 320
June 8,690 250
July 10,652 410
August 7,700 230
Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant.
In your calculations, round the variable rate per employee hour to the nearest cent. If required, round your final answers to the nearest cent.
Required:
1.Using the high-low method, calculate the fixed cost of labor.
$
2.Using the high-low method, calculate the variable rate.
$per employee hour
3.Using the high-low method, construct the cost formula for total labor cost.
Total labor cost = $+ ($ Employee hours)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts