Question: Using Johnson's rule for 2 - machine scheduling, the sequence is: table [ [ Scheduled Order,Job ] , [ 1 , A ] ,

Using Johnson's rule for 2-machine scheduling, the sequence is:
\table[[Scheduled Order,Job],[1,A],[2,F],[3,E],[4,B],[5,D],[6,C]]
For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2 nd operation)= hours (enter your response as a whole number).
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows:
\table[[Job,\table[[Operation],[1(hours)]],\table[[Operation],[2(hours)]]],[A,1,3],[B,10,12],[C,8,7],[D,11,9],[E,4,6],[F,2,13]]
Using Johnson's rule for 2 - machine scheduling,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!