Question: Using Johnson's rule for 2 machine scheduling, the sequence is Scheduled Order Job 2 Six jobs are to be processed through a two-stop operation The

Using Johnson's rule for 2 machine scheduling,
Using Johnson's rule for 2 machine scheduling, the sequence is Scheduled Order Job 2 Six jobs are to be processed through a two-stop operation The first operation involves sanding, and the second involves painting Processing times are as follows: Operation 1 Operation 2 Job Thours) [hours) A 1 3 B 10 12 8 7 D 11 9 E 4 6 F 2 13 3 4 Uw 5 6 For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) hours (orifer your responce a whole number)