Question: Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 E 2 D 3 C 4 A 5 B 6 F For

Using Johnson's rule for 2-machine scheduling, the sequence is:

Scheduled Order

Job

1

E

2

D

3

C

4

A

5

B

6

F

For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) =

3434

hours (enter your response as a whole number).

Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows:

Job

Operation 1 (hours)

Operation 2 (hours)

Upper AA

1010

55

Upper BB

77

44

Upper CC

55

77

Upper DD

33

88

Upper EE

22

66

Upper FF

44

33

Enter your answer in the answer box and then click Check Answer.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!