Question: Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 A, E, F, C, B, D 2 B, E, C, F, A,
Using Johnson's rule for 2-machine scheduling, the sequence is:
| Scheduled Order | Job |
| 1 | A, E, F, C, B, D |
| 2 | B, E, C, F, A, D |
| 3 | F, B, A, E, D, C |
| 4 | B, E, D, A, C, F |
| 5 | E, C, B, F, A, D |
| 6 | C, F, E, B, A, D |
For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = ___ hours (enter your response as a whole number).
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows:
Job Operation 1 (hours) Operation 2 (hours) A 10 8 B 3 4 C 6 2 D 12 7 E 5 1 F 14 13
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts