Question: Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Six jobs are to be processed through a two-step operation. The first operation involves

Using Johnson's rule for 2-machine scheduling,
Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting Processing times are as follows: Job Job A B D E F Operation 1 (hours) 10 7 5 3 2 4 Operation 2 (hours) 5 4 7 8 6 3