Question: Using Johnson's rule for 2-machine scheduling, the sequence is: Six jobs are to be processed through a two-step operation. The first operation involves sanding, and

Using Johnson's rule for 2-machine scheduling, the sequence is: Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting Processing times are as follows: Scheduled Order Job 1 2 Operation 1 (hours) 12 8 5 Operation 2 (hours) 4 3 le