Question: Using LPT priority would result in what sequence for Jobs A, B, C, and D if their process times are 4, 6, 5, 2 respectively?
Using LPT priority would result in what sequence for Jobs A, B, C, and D if their process times are 4, 6, 5, 2 respectively?
| ABCD | ||
| DCBA | ||
| DACB | ||
| DABC | ||
| none of the above |