Question: Using MS Excel, Develop an activity schedule for this project. Adeola would like to determine the project completion time and the critical path for constructing

Using MS Excel, Develop an activity schedule for this project.
Adeola would like to determine the project completion time and the critical path for constructing a standard 3-bedroom residential house. A list of activities and their optimistic, pessimistic, and most probable completion times is given below: Times are in weeks. m Activity Most Probable Immediate Optimistic Pessimistic Predecessor b A 4 6 8 B 3 4 5 C 2 3 4 D 6 7 8 E 2 4 6 B,D F 6 10 14 A,E G 3 6 9 F H 10 11 12 G I 12 16 18 EStep by Step Solution