Question: using MS project or any another project managment software draw the following table as Gant and as Activity on node (AON) and calculate the duration

using MS project or any another project managment software draw the following table as Gant and as Activity on node (AON)

and calculate the duration of the project

No

Activity

Time per week

Previous work

A

Get ideas and opinions on designs and things to consider to be in the laboratory through questionnaires and meetings.

4 weeks

-

B

Processing of project plans, including architectural, mechanical, electrical and interior design plans

4 weeks

A

C

Obtaining the necessary licenses for the project from the licenses of the Ministry of Education and Higher Education, the Ministry of Health and other ministries

8 weeks

B

D

Announcements of tenders and agreement with suppliers to supply laboratory and grade furniture and supply of equipment and equipment

4 weeks

C

E

Announcement of a tender and agreement with a construction contracting company to carry out construction work

4 weeks

C

F

The process of supplying and storing furniture, equipment and equipment

12 weeks

D

G

Construction work

21 weeks

E

H

Taking furniture and laboratory equipment out of stores and installing them in the laboratory

1 week

F,G

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!