Question: Using output from Activity 4: Network Analysis and the additional information provided in the table below , we would like you to create a project

Using output from Activity 4: Network Analysis and the additional information provided in the table below, we would like you to create a project schedule Gantt chart and associated resource profile.

Output From Activity 4: Network Analysis: Using output from Activity 4: Network Analysis

Additional Data:

Using output from Activity 4: Network AnalysisUsing output from Activity 4: Network AnalysisUsing output from Activity 4: Network Analysis

solution. 0/10 DO 000 0 5 0 O A. 1055 04/2 13 E 13 1/3 2/15 1/14 13L13 134 17 5/11/13 B 0 5 8 13 21/8 16 F 16 18 6 24 2/4// ||1 13/G 13 924 15 141/4/11 13 M 13 17 24 Critical path = A-B-C-D Duration = 38 > 11/ 14 13H13 13/28 olclo 1315 28 11////20 13 N 13 124 933 11/15 180 18 29 433 122 137 13 278 35 14//// 19 16/J/16 30 5/35 (2838 O 28 10 38 2225 13 K 13 35 3 38 20%25 13 P13 33 5 38 /float ESEF "/Activity float / Finish 384 235 220/38 box shows. LS/Duration LF Activity ID Start A B C D E F G H I J K L M N Duration (Days) 0 5 8 15 10 2 6 9 3 8 5 3 4 7 9 Successor Activity A,E,L B C D Finish F, G H H I, J K K Finish M N, O P Resource (People) 0 2 2 2 2 3 1 4 2 2 3 3 01 5 5 5 O P Finish 4 LO 5 O P Finish 6 5 Reflect on what the Gantt chart tells you as a project manager during the execution phase of the project. 1. 2. 3. 4. How many activities are there in total? What proportion of activities are critical? How many critical activities would you need to monitor on any one day? What is the largest number of parallel activities that are scheduled to happen at once

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!