Question: Using Process 4.7 Close Project or Phase from PMBOK 6th edition........In the case study 'Fond du lac'(A) Explain how you would improve the scenario depicted
Using Process 4.7 Close Project or Phase from PMBOK 6th edition........In the case study 'Fond du lac'(A) Explain how you would improve the scenario depicted in this case study using this process.(B). Specifically which tool or technique would you implement? Be specific, and properly identify the tool or technique.(C). Explain why you would choose to use this tool or technique.

Construction Manager/ PHWA's Eoslem Federal Lands Highway Division requested delivery assistance from CFLHD in December 2012. Keys to Success General Contractor CALHD scoped the project that month, and committed Every ingenu to having the road reopened by the end of the 2013 Utilize contractor knowledge of cost. construction season. avolablity, capacity and quantities of Counts -invention PROJECT CASE STUDY materials, labor and equipment to maintain The repair site was approved for funding under the schedule. Emergency Relief for Federally Owned (FRFO] Roads Program, The ERFO program repairs ore intended to be Identify potential risks, including financial, and Construction Manager/General Contractor Method Hastens Delivery replace-in-kind to pre-disaster conditions; however, the construction methods to mitigate these risks existing culvert at this location was undersized and would during the design process. of Critical Bridge for Fond du Lac Reservation likely fail again in the future from embankment piping, overlapping, or saturation any time a 10-to 20-year storm event occurs. The embankment had falled in the past of During June 2012, record amounts of rainfall in the this same location, approximately 20 years ago. The existing culvert was also impairing fish passage in Fond du Lac Duluth area of northeastern Minnesota brought about Creek, a designated trout stream. a 500-year flood event that caused more than $17.8 million in damage to public infrastructure across CFLHD performed a life cycle cast analysis to determine the most cost effective engineering solution. Options the state. Swollen rivers and flash floods washed considered in the analysis included box culverts, plate arches, a bridge, and replace in kind. Ultimately. the bridge away or damaged several bridges and rendered was selected based on life cycle cost. minimization of environmental impacts, and agency input. large sections of roadway impassable, including a primary road on the Fond du Lac Reservation that The ambitious project schedule involved repairing damage to the existing roadway and environment and was essential for access to homes and emergency constructing a new bridge before the onset of winter weather. There were also cultural and natural resource issues services. to consider, such as maintaining fish passage in the existing trout stream. With these considerations, CM/GC was chosen as the project delivery method to help mitigate schedule risks and improve constructability. The CM/GC With Fond du Lac Reservation residents needing process allowed valuable input from the contractor on availability of materials, especialy considering the significant this route restored as soon as possible, the Federal demand due to repairs underway following the floods, and on locally viable construction methods. It also allowed Highway Administration's Central Federal Lands of rood al i creek creaming britt of early procurement of long lead-time items, which helped maintain the project schedule. Highway Division [CFLHD) developed an innovative project deployment solution using the Construction Development of the plan, specification and estimate (PS&E) package and construction occurred within a 10-month Manager/ General Contractor (C/GC) method. period. Construction began in July 2013, and final inspection was completed in October 2013. The washed out which saved time and money in reporing and doverd was replaced with a single span, pre-stressed, reinforced concrete girder bridge, which satisfied hydrologic building a new bridge on this vital road, and hydraulic design standards while accommodating fish passage. The total construction cost was $1.5 milion. Bridging the Gap in Reservation Road Input from the contractor during design development allowed the project to be delivered within budget and minimized the number of construction modrications. The expedited schedule not only met the expectations of the The 2012 storm event substantialy damaged Cariton client, the Ferd du Lac Tribe, but also saved approximately $150,000 in engineering costs, County Road 1 14, locally known as Reservation Road at g 60-inch pipe culver! crossing comying ACDITIONAL RESOURCES fond du Lac Creek underneath, The event caused FHWA CM/GC Project Delivery Program Guide: http://www.thwa.dot.gov/construction/cait/cm.cim water to back up of the culvert and collect along the macway embankment, resulting in failure of the IFHWA Accelerating kinovation CM/GC web page: slope. and ultimately tha roadway. An approximately http /rowwithwa dot.you/everydaycourts/edetwo/2012/emac.com The foot stretch of the road was completely washed The CM GC process helped expedite delivery be phen bridge out, leaving it impassable and closed. while saving appiokragiely 51 50 dog in enginewa bcout For additional ivornichon Wendy longley Michael Davies about this BDC initiative. BENEFITS OF CONSTRUCTION MANAGER/GENERAL CONTRACTOR hope Manager Director, Office of Project Delivery plaine contact FHWA, CHAD [OFFM-14] FHWA. CFUND Savings Wendy.Longleptidol gur Michael Dovienidal go conthuckaplay. material avaladata odds is mitpote there during aireian and and local conttruction techniques hers 45. Department of farsportation construction manton fin combustion scheadle for change Corn Federal Highway Administration www /hwa.dot.gov/everydaycount
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
