Question: Using software of your choice ( excel , word or PowerPoint ) or paper, draw a Project Network Diagram ( PND ) based on the
Using software of your choice excel word or PowerPoint or paper, draw a Project Network Diagram PND based on the project information below.
Complete a forward and backward pass of the network. For each activity show the early start, early finish, late start, late finish.
Calculate the slack for each activity.
Identify the Critical Path for the project.
You are the project manager for this project and your team will receive a $ bonus for completing the project in working days. You will also be penalized $day for every day over the day limit Based on your project planning, do you expect to receive a bonus or penalty on this project? If so how much?
If you were to reduce the project duration, which activitys would you crash? Justify your choice.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock