Question: Using soltware of your choice ( excel , word or PowerPoint ) or paper, draw a Project Network Diagram ( PND ) based on the

Using soltware of your choice (excel, word or PowerPoint) or paper, draw a Project Network Diagram (PND) based on the project information below.
\table[[ID,Description,Predecessor,Time (days)],[A,Prepare site,None,2],[B,Pour foundation,A,3],[C,Erect frame,B,4],[D,Roof,C,4],[E,Windows,C,1],[F,Doors,C,1],[G,Electrical,C,3],[H,Rough-in-frame,D, E, F, G,2],[I,Door opener,F, G,1],[J,Paint,H, I,2],[K,Cleanup,J,1]]
Complete a forward and backward pass of the network. For each activity show the early start early finish, late start late finish.
Carculate the slack for each activity.
Identify the Critical Path for the project.
You are the project manager for this project and your team will receive a $1000 bonus for completing the project in 17 working days. You wil also be penalized $500/day for every day over the 17-day frevit. Based en your project planning, do you expect to recelve a bonus or penalty an this project? If sa how much?
it you were to reduce the project duratian, which
Using soltware of your choice ( excel , word or

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!