Question: Using Table 1, the probability that the project could be completed in 23 weeks or less is approximately A. 0.94 B. 0.89 C. 0.87 D.
Using Table 1, the probability that the project could be completed in 23 weeks or less is approximately A. 0.94 B. 0.89 C. 0.87 D. 0.91