Question: Using Table 3, a) Under normal conditions: what is the earliest the project can be completed; what is the critical path; what is the cost?

Using Table 3, a) Under "normal" conditions: what is the earliest the project can be completed; what is the critical path; what is the cost? (b) Suppose you wanted to complete the project two weeks earlier than under normal conditions. What activity(ies) would you have to speed up. How much would it add to the cost of the project? (c) Under "crash" conditions: what is the earliest the project can be completed; what is the maximum it will cost to complete it in this time. (no easing of activities)