Question: Using the 0-50-100 rule for tracking schedule progress has what risk? If many long tasks are started concurrently, the EV is initially overstated and misleading.

Using the 0-50-100 rule for tracking schedule
Using the 0-50-100 rule for tracking schedule progress has what risk? If many long tasks are started concurrently, the EV is initially overstated and misleading. If many long tasks are started concurrently, as the work progresses eventually the EV will become understated and misleading. The longer the task duration, the less accurate the schedule status. All answers are correct