Use the Critical Path Method to answer the next three questions. (show your work without which...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Use the Critical Path Method to answer the next three questions. (show your work without which answers will not be accepted) A project consists of the following activities: Table 9.11 Activity Activity Predecessor A B с D E F A A B C D, E Time (weeks) 5 8 3 7 10 9) (S) (show your work) Using Table 9.1, the earliest start time for activity F is: A) 14 weeks. B) 30 weeks. C) 20 weeks. D) 13 weeks. 4 10) (S) (show your work) Using Table 9.1, the critical path for this project consists of activities: D) A-B-C-F. A) A-B-C-D-E-F. B) A-C-E-F. C) A-B-D-F. 11) (S) (show your work) Using Table 9.1, the time complete the entire project is: A) 20 weeks. B) 36 weeks. C) 30 weeks. D) 39 weeks. Use the Critical Path Method to answer the next three questions. (show your work without which answers will not be accepted) A project consists of the following activities: Table 9.11 Activity Activity Predecessor A B с D E F A A B C D, E Time (weeks) 5 8 3 7 10 9) (S) (show your work) Using Table 9.1, the earliest start time for activity F is: A) 14 weeks. B) 30 weeks. C) 20 weeks. D) 13 weeks. 4 10) (S) (show your work) Using Table 9.1, the critical path for this project consists of activities: D) A-B-C-F. A) A-B-C-D-E-F. B) A-C-E-F. C) A-B-D-F. 11) (S) (show your work) Using Table 9.1, the time complete the entire project is: A) 20 weeks. B) 36 weeks. C) 30 weeks. D) 39 weeks.
Expert Answer:
Answer rating: 100% (QA)
9correct answer is C20 weeeks 10correct answer is CABDF 11cor... View the full answer
Related Book For
Managing Supply Chain and Operations An Integrative Approach
ISBN: 978-0132832403
1st edition
Authors: Thomas Foster, Scott E. Sampson, Cynthia Wallin, Scott W Webb
Posted Date:
Students also viewed these general management questions
-
A project consists of the following tasks, with task times in weeks. Use the data provided to identify the projects critical path. ask PrecedingL ask Preceding Tasks A None 8 910 B None 5 912 CA DIB...
-
A project consists of the following activities, normal durations (days), immediate predecessors, cost per day to crash ($000/day), and available days to crash. a. Draw the precedence network. b....
-
Draw the AON and use the Critical path method to compute the CP, and total slack. Use PERT to analyze the chance the delays on CP activities does not push the project duration beyond 35 days. x: is a...
-
Give the approximate temperature at which creep deformation becomes an important consideration for each of the following metals: nickel, copper, iron, tungsten, lead, and aluminum.
-
Name and describe the steps in the supplier selection and evaluation process.
-
Carla is a 14-year-old female who lives with hermom and 17-year-old brother. She has had annual preventive healthcare from birth and has grown along average height and weight trends. Her medical...
-
What are the benefits of using value management in projects?
-
Pember Inc. is a retailer operating in Edmonton, Alberta. Pember uses the perpetual inventory method. Assume that there are no credit transactions; all amounts are settled in cash. You are provided...
-
Evaluate the definite integral 5 L (8x+6)dz skmistor
-
Assume that all individuals have identical preferences but some individuals are wealthier than others. Assume there is a single public good and a single private good. a. Show diagrammatically how you...
-
Was first introduced to provide businesses with a networking option. O Linux O Unix O Windows NT O Netware Task(s) which should be done on a frequent basis. Checklists Scheduling O Backup & Recovery...
-
ArbreCorp Ltee is a sawmill operation in Quebec that is owned by a major forest products company but operates independently of the parent company. It was built 30 years ago, and completely updated...
-
Taylor Pty Ltd is based in Brisbane and sells glamping yurt tents imported from China at a cost of $150 each plus import duties and other costs of $60. These purchase and import costs are paid cash...
-
Poor nations invest in the fundamental drivers of productivity growth, while rich nations try to use technological advancements to boost productivity. In groups of three or four, consider your own...
-
Companies can shift physical resources and capital relatively easily among national markets where labor is cheaper. But laborers generally face greater difficulty moving to other countries for higher...
-
Imagine that the nations of the world suddenly cut off all trade with one another and the people in each nation were able to consume only products their own nation produced. What products previously...
-
A firm uses two inputs x and y, and their profit function is P(x,y)=3xy-2x+y. Input x costs $2 each and y costs $1 each and they are constrained to spend a total of $100 on inputs. If the firm wants...
-
The overall reaction and equilibrium constant value for a hydrogenoxygen fuel cell at 298 K is 2H 2 (g) + O 2 (g) 2H 2 O(l) K = 1.28 10 83 a. Calculate E cell and G 8 at 298 K for the fuel cell...
-
A company distributes a medical device to hospitals and clinics throughout North America. The device is used in a variety of applications. One critical component of the device is its overall quality....
-
A company currently has two stocking locations that hold a total of 8000 units of safety stock inventory. If the company expands to six stocking locations, what would be the new safety stock...
-
Briefly describe what is meant by nonrandom variation in statistical process control.
-
Reverse-current readings (in nanoamperes) are made at the location of a transistor on an integrated circuit. A sample of size 10 is taken every half hour. Since some of the units may prove to be...
-
In order to establish control charts for an extraction job, 30 samples of five measurements of the extracted ores are taken, and the results are \(\overline{\bar{x}}=25.96\) tons and \(\bar{s}=1.5\)...
-
If the sample standard deviations instead of the sample ranges are used to estimate \(\sigma\), the control limits for the resulting \(\bar{x}\) chart are given by \(\overline{\bar{x}} \pm A_{1}...
Study smarter with the SolutionInn App