Question: Use the Critical Path Method to answer the next three questions. (show your work without which answers will not be accepted) A project consists

Use the Critical Path Method to answer the next three questions. (show 

Use the Critical Path Method to answer the next three questions. (show your work without which answers will not be accepted) A project consists of the following activities: Table 9.11 Activity Activity Predecessor A B D E F A A B C D, E Time (weeks) 5 8 3 7 10 9) (S) (show your work) Using Table 9.1, the earliest start time for activity F is: A) 14 weeks. B) 30 weeks. C) 20 weeks. D) 13 weeks. 4 10) (S) (show your work) Using Table 9.1, the critical path for this project consists of activities: D) A-B-C-F. A) A-B-C-D-E-F. B) A-C-E-F. C) A-B-D-F. 11) (S) (show your work) Using Table 9.1, the time complete the entire project is: A) 20 weeks. B) 36 weeks. C) 30 weeks. D) 39 weeks.

Step by Step Solution

3.55 Rating (176 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

9correct answer is C20 weeeks 10correct answer is CABDF 11cor... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!