Question: Use the Critical Path Method to answer the next three questions. (show your work without which answers will not be accepted) A project consists
Use the Critical Path Method to answer the next three questions. (show your work without which answers will not be accepted) A project consists of the following activities: Table 9.11 Activity Activity Predecessor A B D E F A A B C D, E Time (weeks) 5 8 3 7 10 9) (S) (show your work) Using Table 9.1, the earliest start time for activity F is: A) 14 weeks. B) 30 weeks. C) 20 weeks. D) 13 weeks. 4 10) (S) (show your work) Using Table 9.1, the critical path for this project consists of activities: D) A-B-C-F. A) A-B-C-D-E-F. B) A-C-E-F. C) A-B-D-F. 11) (S) (show your work) Using Table 9.1, the time complete the entire project is: A) 20 weeks. B) 36 weeks. C) 30 weeks. D) 39 weeks.
Step by Step Solution
3.55 Rating (176 Votes )
There are 3 Steps involved in it
9correct answer is C20 weeeks 10correct answer is CABDF 11cor... View full answer