Question: Using the Activity 2 worksheet and based on the baseline schedule provided, what is the Free Float (FF) for activity F? B FS-2 C 10

Using the Activity 2 worksheet and based on the

Using the Activity 2 worksheet and based on the baseline schedule provided, what is the Free Float (FF) for activity F? B FS-2 C 10 10 A FS+2 D E H 10 5 5 5 SS+5 F G 10 10 a. O b. 2 C. 1 d. 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock