Question: Using the BOM shown below, 3 weeks B (4) 1 week D (2) C (3) 2 weeks 2 weeks E(3) F(3) 3.3 weeks 4.3 weeks

Using the BOM shown below, 3 weeks B (4) 1 week D

Using the BOM shown below, 3 weeks B (4) 1 week D (2) C (3) 2 weeks 2 weeks E(3) F(3) 3.3 weeks 4.3 weeks C (4) 2 weeks E(1) 3.3 weeks What is the cumulative lead time for end item A? (Round your answer to 1 decimal place.) Cumulative lead time weeks This is a numeric cell, so please enter numbers only