Question: Using the chart of activity data provided, what is expected standard deviation for activity B is Time (weeks) Activity Optimistic Most Likely Pessimistic A 9

Using the chart of activity data provided, what is expected standard deviation for activity B is

Time (weeks)
Activity Optimistic Most Likely Pessimistic
A 9 12 21
B 13 21 23

A. 10 weeks

B. 3.33 weeks

C. 2.78 weeks

D. 1.67 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!