Question: Using the chart of activity data provided, what is expected standard deviation for activity B is Time (weeks) Activity Optimistic Most Likely Pessimistic A 9
Using the chart of activity data provided, what is expected standard deviation for activity B is
| Time (weeks) | |||
| Activity | Optimistic | Most Likely | Pessimistic |
| A | 9 | 12 | 21 |
| B | 13 | 21 | 23 |
A. 10 weeks
B. 3.33 weeks
C. 2.78 weeks
D. 1.67 weeks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts