Question: Using the complexity weighting scheme shown in Table 5.2 (p. 138) and the function point complexity weighted table shown below, estimate the total function point

Using the complexity weighting scheme shown in Table 5.2 (p. 138) and the function point complexity weighted table shown below, estimate the total function point count for this project. Assume historical data suggests that eight function points equal one person a month and six people can work on the project. Your table should look like the bottom part of Table 5.3 (p. 138). Where possible, be sure to use formulas.

Underneath your table, respond to the following questions:

What is the estimated project duration?

If 7 people are available for the project, what is the estimated project duration (to the nearest tenth)?

If the project must be completed in 4 months, how many people are needed for the project (to the nearest tenth)?

Complexity Weight Table

Number of inputs 30 Rated complexity high

Number of outputs 20 Rated complexity average

Number of inquiries 10 Rated complexity low

Number of files 15 Rated complexity average

Number of interfaces 10 Rated complexity low

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!