Question: Using the cost data for Project X and Project Y below, conduct a Present Worth Analysis to calculate the Present Worth of Project X

Using the cost data for Project X and Project Y below, conduct 

Using the cost data for Project X and Project Y below, conduct a Present Worth Analysis to calculate the Present Worth of Project X at time 0 over LCM years of the life of both X and Y. Given 8% per year interest rate. Y First Cost -60,000 -150,000 Annual Cost -12,000 -7,000 Salvage 5,000 80,000 Value Life 10 Infinity Present Worth of Project X is closest to which answer? -230,226 -138,205 -269.131 O -257,458

Step by Step Solution

3.59 Rating (153 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

2B 138205 Present worth of x is 138205 Pv of 10 years 8 ... View full answer