Question: Using the Cost Reports Processing Time chart, answer the following question: 1. If Sara takes the twelve reports in the chart as representing the sequence

Using the Cost Reports Processing Time chart, answer the following question:

1. If Sara takes the twelve reports in the chart as representing the sequence in which the report was received, how long will it take to get all twelve reports in the system?

2. Is there a better sequence in which to process the reports? Develop a better schedule and calculate how much time is saved.

3. Show any time periods when Sara or the data entry people are idle.

Cost Reports Process Time (minutes)
Report Review Time Data Entry Time
Specialty Restaurant I 12 10
Specialty Restaurant II 14 16
Wine I 17 18
Wine II 20 22
Wine III 12 15
Bar Service I 10 15
Bar Service II 25 32
Bar Service III 22 28
Bar Service IV 16 20
Shore Excursions 30 35
Gift Shops 24 30
Salon/Spa 18

25

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!