Using the Cost Reports Processing Time chart, answer the following question: 1. If Sara takes the twelve
Fantastic news! We've Found the answer you've been seeking!
Question:
Using the Cost Reports Processing Time chart, answer the following question:
1. If Sara takes the twelve reports in the chart as representing the sequence in which the report was received, how long will it take to get all twelve reports in the system?
2. Is there a better sequence in which to process the reports? Develop a better schedule and calculate how much time is saved.
3. Show any time periods when Sara or the data entry people are idle.
Cost Reports Process Time (minutes) | ||
Report | Review Time | Data Entry Time |
Specialty Restaurant I | 12 | 10 |
Specialty Restaurant II | 14 | 16 |
Wine I | 17 | 18 |
Wine II | 20 | 22 |
Wine III | 12 | 15 |
Bar Service I | 10 | 15 |
Bar Service II | 25 | 32 |
Bar Service III | 22 | 28 |
Bar Service IV | 16 | 20 |
Shore Excursions | 30 | 35 |
Gift Shops | 24 | 30 |
Salon/Spa | 18 | 25 |