Question: Using the Critical Path Method (CPM) in developing a Project Management Network Diagram, what is the critical path for the following project? Activity Precedent Acvity
Using the Critical Path Method (CPM) in developing a Project Management Network Diagram, what is the critical path for the following project?
| Activity | Precedent Acvity | Completion Time |
| A | NONE | 3 |
| B | A | 2 |
| C | B | 4 |
| D | B | 5 |
| E | C | 6 |
| F | E | 2 |
| G | E | 2 |
| H | D | 6 |
| I | D | 5 |
| J | G, H | 4 |
| K | F, J | 3 |
| L | I | 4 |
| M | L | 2 |
| N | K, M | 1 |
| a) A-B-C-E-F-K-N | ||
| b) A-B-C-E-G-J-K-N | ||
| c) A-B-D-H-J-K-N | ||
| d) A-B-D-I-L-M-N | ||
| e) A-B-D-H-G-J-K-N |
Using the Project Management Network Diagram developed in question 3, what is the estimated completion time for the project?
The below table outlines the activities, precedent activities, and the completion times of activities (in weeks).
| Activity | Precedent Acvity | Completion Time |
| A | NONE | 3 |
| B | A | 2 |
| C | B | 4 |
| D | B | 5 |
| E | C | 6 |
| F | E | 2 |
| G | E | 2 |
| H | D | 6 |
| I | D | 5 |
| J | G, H | 4 |
| K | F, J | 3 |
| L | I | 4 |
| M | L | 2 |
| N | K, M | 1 |
| a) 23 weeks | ||
| b) 24 weeks | ||
| c) 25 weeks | ||
| d) 26 weeks | ||
| e) 27 weeks |