Question: Using the Critical Path Method (CPM) in developing a Project Management Network Diagram, what is the critical path for the following project? Activity Precedent Acvity

Using the Critical Path Method (CPM) in developing a Project Management Network Diagram, what is the critical path for the following project? Activity Precedent Acvity Completion Time A NONE 3 B A 2 C B 4 D B 5 E C 6 F E 2 G E 2 H D 6 I D 5 J G, H 4 K F, J 3 L I 4 M L 2 N K, M 1 a) A-B-C-E-F-K-N b) A-B-C-E-G-J-K-N c) A-B-D-H-J-K-N d) A-B-D-I-L-M-N e) A-B-D-H-G-J-K-N 1 points QUESTION 4 Using the Project Management Network Diagram