Question: Using the current specifications, resurfacing a road will cost $1.5M initially, need $120K in annual maintenance, and need to be resurfaced every 10 years.
Using the current specifications, resurfacing a road will cost $1.5M initially, need $120K in annual maintenance, and need to be resurfaced every 10 years. A proposed new specification is expected to be more resistant to wear. The resurfacing cost will be $2.1M with $90K in annual maintenance and resurfacing every 15 years. (a) Develop a choice table for interest rates from 0% to 25%. (b) If the highway department's interest rate is 6%, which specification is preferred?
Step by Step Solution
There are 3 Steps involved in it
To solve this problem we need to compare the present worth of both alternatives over their life cycl... View full answer