Question: Using the data below, construct a schedule in MS Project. Show where the project is ahead and/or behind schedule. Be specific. Which activities did the
Using the data below, construct a schedule in MS Project. Show where the project is ahead and/or behind schedule. Be specific. Which activities did the best? Which had the most problems?
| Planned Start | Planned Finish | Actual Start | Actual Finish |
| 8/31 | 9/5 | 8/31 | 9/5 |
| 8/25 | 9/8 | 8/25 | 9/8 |
| 9/5 | 9/8 | 9/5 | 9/8 |
| 8/25 | 9/2 | 8/26 | 9/3 |
| 8/26 | 8/27 | 8/28 | 8/29 |
| 8/25 | 9/8 | 8/28 | 9/8 |
| 8/25 | 9/6 | 8/29 | 9/6 |
| 8/25 | 9/1 | 8/29 | 9/6 |
| 9/1 | 9/2 | 9/5 | 9/11 |
| 9/1 | 9/6 | 9/5 | 9/11 |
| 9/1 | 9/8 | 9/6 | 9/14 |
| 9/8 | 9/15 | 9/13 | 9/22 |
| 8/25 | 10/26 | 8/31 | 10/31 |
| 8/25 | 9/16 | 8/31 | 9/23 |
| 9/16 | 9/29 | 9/23 | 10/9 |
| 9/16 | 9/19 | 9/23 | 9/25 |
| 9/20 | 9/28 | 9/30 | 10/6 |
| 9/20 | 9/21 | 9/30 | 10/21 |
| 9/22 | 9/28 | 10/3 | 10/28 |
| 9/16 | 9/27 | 9/26 | 10/27 |
| 9/16 | 9/20 | 9/27 | 10/10 |
| 9/21 | 9/26 | 10/6 | 10/16 |
| 9/28 | 10/6 | 10/15 | 11/6 |
| 9/28 | 10/5 | 10/22 | 11/5 |
| 10/7 | 10/10 | 11/7 | 11/20 |