Question: Using the data below, construct a schedule in MS Project. Show where the project is ahead and/or behind schedule. Be specific. Which activities did the

Using the data below, construct a schedule in MS Project. Show where the project is ahead and/or behind schedule. Be specific. Which activities did the best? Which had the most problems?

Planned Start 8/31 8/25 9/5 8/25 Planned Finish 9/5 9/8 9/8 9/2

Actual Start 8/31 8/25 9/5 8/26 Actual Finish 9/5 9/8 9/8 9/3

image text in transcribed

Planned Start 8/31 8/25 9/5 8/25 Planned Finish 9/5 9/8 9/8 9/2 Actual Start 8/31 8/25 9/5 8/26 Actual Finish 9/5 9/8 9/8 9/3