Question: Using the data from #1 in the image, may you please help me answer questions #2 & #3.2. Given the data above, if we crashed
Using the data from #1 in the image, may you please help me answer questions #2 & #3.2. Given the data above, if we crashed the schedule for ten weeks, how much would the new project cost?a. $20,600b. $21,800c. $23,900d. $24,700e. $27,7003. Given the data above, if we crashed the schedule for twelve weeks, how much would the new project cost?a. $20,600b. $21,800c. $23,900d. $24,700e. $27,700