Question: Using the figure below, answer the following: 1. Calculate the ES, EF, LS, and LF times and the slack time for each activity. 2. Identify

Using the figure below, answer the following:

1. Calculate the ES, EF, LS, and LF times and the slack time for each activity.

2. Identify the critical path for the project.

3. Can the project be completed in 30 weeks?

4. Assume that "Systems Analysis" actually finished at 8 weeks, "Design Input & Output" actually finished at 13 weeks, and "Design Database" actually finished at 18 weeks. Recalculate the expected project completion time.

5. Which activities would you focus on to get the project back on schedule?

Using the figure below, answer the following:1. Calculate the ES, EF, LS,

Develop Input Screens Design 5 8 Input & Output Problem 3 System 3 Develop Test Implement Definition Analysis Output System System Reports 2 2 5 6 10 8 5 Design Develop Database Database 4 15 7 2 Project Target Completion is 30 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!