Question: Using the figure below, perform resource-limited scheduling. Assume that you only have three workers available at any given time. What is the new completion date

Using the figure below, perform resource-limited scheduling. Assume that you only have three workers available at any given time. What is the new completion date for the project?

Using the figure below, perform resource-limited

Task 1 (2 workers) Task 2 (1 worker) Task 3 (3 workers) Task 4 (2 workers) - Task 5 (1 worker) Task 6 (3 workers) Day 1 2 3 4 5 6 7 8 9 10 Workers 6 6 6 4 2 3 3 4 3 3