Question: Using the following activities and relationships, construct the following: 1. A network precedence diagram. Only 1 jump is authorized. (2.5%) 2. Determine and tabulate the
Using the following activities and relationships, construct the following: 1. A network precedence diagram. Only 1 jump is authorized. (2.5%) 2. Determine and tabulate the ES, EF, LS, LF, TF, & FF for all activities. (90%) 3. Draw the critical path with double lines or a highlighter on the precedence diagram. (5%) 4. Determine the project duration (2.5%) 5. Extra 5%: What is wrong with this network precedence diagram and why? Dur Predecessor(s) ES EF LS LF Act ID TF FF > 5 B 6 3 B D 4 C(SSI) E 5 D(FF3), G F 7 A(SS2) 2 F.J H 1 2 H J 7 I K 2 FJ L 5 H M 4 L(SSI) N KM 2 E (FFS) N(SS2)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
