Question: Using the following BOM (in its tree form), complete the following MRP analysis, knowing that the lead time is one week for each of the

Using the following BOM (in its tree form), complete the following MRP analysis, knowing that the lead time is one week for each of the components (including the final product).

You have an MPS of 100 units of A in week 5 and at the beginning there are already 20 units of B. The order quantity is batch-to-batch.

Using the following BOM (in its tree form),

Note:

please do it in excel, (with formulas), and show the formulas

A B(2) C(1) D(1) E(1) D(2) F(1) 1 2 3 4 4 5 Week Gross Requirements Scheduled Receipts Projected Available Net Requirements Planned Order Receipt Planned Order Release

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!