Question: Using the following information, determine the minimum cycle time for the assembly line: tTotal number of tasks on the assembly line is 34 Longest task
Using the following information, determine the minimum cycle time for the assembly line:
tTotal number of tasks on the assembly line is 34
Longest task is 4.7 minutes
The total time for all tasks is 92 minutes
the line will operate for 615 minutes per day
Please show calculations as well