Question: Using your results from Problem 6, a) Calculate the probability that the project will be completed in 32 weeks. b) Calculate the probability that the
Using your results from Problem 6,
a) Calculate the probability that the project will be completed in 32 weeks.
b) Calculate the probability that the project will be completed in 35 weeks.
Data from Problem 6
Using the information given, calculate the variance for each of the project activities.

Activity Optimistic Time Estimate (weeks) 2 2.5 5 3 4 2 4 6 4 2 A B C D E F G H I J Most Likely Time Estimates (weeks) 3 4 7 5 7 5 5 6 8 3 Pessimistic Immediate Time Estimates Predecessor(s) (weeks) 5 5 8 7 14 8 6 8 11 3 none A A B. C B, C D E F G H, I
Step by Step Solution
3.47 Rating (150 Votes )
There are 3 Steps involved in it
a b Pproject ... View full answer