Question: Using the following project information The critical path is A-C.E.G.F-J (a) Calculate the probability that the project will be completed in 32 weeks. (Round your

Using the following project information The critical path is A-C.E.G.F-J (a) Calculate the probability that the project will be completed in 32 weeks. (Round your answer to 4 decimal ploces, es. 1.7945.) P(project $32) (b) Calculate the probability that the project will be completed in 36 weeks. (Round your answer to 4 decimal ploces, es. 1.7945) P(project s36)= eTextbook and Media Attempts: 0 of 3 used
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
