Question: Using the following table, calculate the Late Start for Task A Task Predecessor Duration (days) A - 61 B A 53 C - 29 D
Using the following table, calculate the Late Start for Task A
| Task | Predecessor | Duration (days) |
| A | - | 61 |
| B | A | 53 |
| C | - | 29 |
| D | - | 15 |
| E | B | 25 |
| F | B,C | 54 |
| G | E,F | 52 |
| H | F | 17 |