Question: Using the following table, if the project team will work a standard week work and that all the tasks will start as soon as possible:

Using the following table, if the project team will work a standard week work and that all the tasks will start as soon as possible: 1. Draw the corresponding activity network 2. Show the critical path. 3. What is the minimum time required to finish the project? 4. If task C (Programming) is delayed for 2 weeks, will the project finish on time? Why? If task (D Telecoms) is delayed for 2 weeks, will the project finish on time? Why?

Activity Duration

(week) Precedents A Requirement Analysis 5 - B System design 15 A C Programming 25 B D Telecoms 15 B E Hardware Installation 30 B F Integration 10 C, D G System Testing 10 E, F H Training and support 5 G I Handover and Go-Live 5 H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!