Question: Activity Duration (week) Precedents A Requirement Analysis 5 - B System design 15 A C Programming 25 B D Telecoms 15 B E Hardware Installation
| Activity | Duration (week) | Precedents |
| A Requirement Analysis | 5 | - |
| B System design | 15 | A |
| C Programming | 25 | B |
| D Telecoms | 15 | B |
| E Hardware Installation | 30 | B |
| F Integration | 10 | C, D |
| G System Testing | 10 | E, F |
| H Training and support | 5 | G |
| I Handover and Go-Live | 5 | H |
Using the following table, if the project team will work a standard week work and that all the tasks will start as soon as possible: 1. Draw the corresponding activity network 2. Show the critical path. 3. What is the minimum time required to finish the project? 4. If task C (Programming) is delayed for 2 weeks, will the project finish on time? Why? If task (D Telecoms) is delayed for 2 weeks, will the project finish on time? Why?