Question: Using the following table, what is the earliest expected time of completion of the whole project? Activity Immediate Predecessor) A A B D E F

Using the following table, what is the earliest
Using the following table, what is the earliest expected time of completion of the whole project? Activity Immediate Predecessor) A A B D E F G H B D E Expected Time (days) 2 1 2 1 2 1 3 3 8 D G D FH 1 4 1 OA) 9 days OB) 11 days C) 14 days D) 28 days