Question: Using the formula provided and the information on the MRP grid below, calculate the numeric answer to the questionWhat is the net requirement quantity for
Using the formula provided and the information on the MRP grid below, calculate the numeric answer to the questionWhat is the net requirement quantity for item M in week Note: Net requirements occur when the gross requirements is larger than all currently planned sources of supply for the period To put this in the form of a formula: Formula: Net requirements in period x the greater of or gross requirements in period scheduled receipts in period prior period's PABItem Number Gross Requirements Scheduled Receipts Projected Available M Net Requirements Planned Order Receipts Planned Order Releases Week