Question: Using the formula provided and the information on the MRP grid below, calculate the numeric answer to the question: What is the net requirement quantity
Using the formula provided and the information on the MRP grid below, calculate the numeric answer to the question: What is the net requirement quantity for item N in week Note: Net requirements occur when the gross requirements is larger than all currently planned sources of supply for the period. To put this in the form of a formula: Formula: Net requirements in period the greater of or gross requirements in period xscheduled receipts in period prior period's PABItem Number Gross Requirements Scheduled Receipts Projected Available N Net Requirements Planned Order Receipts Planned Order Releases Week