Question: Using the given information calculate the gross requirements for each of the components when the company palsn to build 100 of its Q models if

Using the given information calculate the gross requirements for each of the components when the company palsn to build 100 of its Q models if you have these inventories 150 uunits of component T and 200 units of component R

Ussage per parent Lod Time ( weeks )

Q 2

R 2 3

S 1 4

T 3 2

Y 1 2

V 1 3

Z 3 2