Question: Using the given information: Please draw a network diagram, specify the workstation cycle time, specify the longest task route, specify the efficiency of the line,
Using the given information: Please draw a network diagram, specify the workstation cycle time, specify the longest task route, specify the efficiency of the line, and advise what is the theoretical minimum number of workstations (N) for this problem.
An assembly line is to operate eight hours per day with the desired output of 300 units per day. The following table contains information on this product's task times, and precedence relationship Immediate Activity Time Activity Predecessor second A None 60 B None 30 A 20 B,C 30 CD 60 E 30 90 F,G 30 D E F G B H
Thank you for your assistance. You are appreciated.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock